Can I colour code to easily highlight tasks for multiple task managers?
For upcoming training course dates see: Pricing & availability
RE: Project
Hi Alyson
Thank you for your question. One approach might be to set a flag for a particular task.
To do this insert a column into the Gantt chart view and set it to one of the spare Flag fields (eg Flag 1). Then from the Format menu choose Format Bar Styles and create a new style at the bottom of the list has the formatting you would like to apply just for this resource. In the "Show for" section set it to apply for Flag 1.
Now when you set Flag 1 to Yes for your tasks you will find the associated bar picks up the formatting from the style.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
|