Can you explan PERT analysis
For upcoming training course dates see: Pricing & availability
RE: PERT analysis
Hi Jonathan
Thank you for your question. PERT analysis stands for Program Evaluation Review Technique and is a tool to help estimate the duration for tasks.
From the View menu choose Toolbars > Pert Analysis
From here you can set your Optimistic, Pessimistic and Exptected durations for your task. Clicking on calculate will make Project work out a weighted average based on the three values to create a new estimated duration for your task.
I hope this helps - do let us know if you have any further questions.