Project

resolvedResolved · Low Priority · Version 2007

replyReply Fri 1 May 2009, 15:16Delegate Mark said...

Mark has attended:
Project Intro Intermediate course

Project

How do I clear multiple deadlines in one go?

For upcoming training course dates see: Pricing & availability

replyReply Tue 5 May 2009, 09:30Trainer Simon said...

RE: Project

Hi Mark,

Thank you for your question.

Select the desired tasks first and click the Task Information button on the toolbar or choose Task Information from the Project menu.

Go to the Advanced Tab and type NA in the Deadline box.

I hope this answers your question.

Regards

Simon

 

Please browse our web site to find out more about
project server consultants and other Microsoft training courses.

Ms project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard