Resources, work and duration

resolvedResolved · High Priority · Version 2007

replyReplyMon 8 Jun 2009, 15:36Delegate Stuart said...

Resources, work and duration

Hi Andrew,

During our recent training session we discussed wanting to fix the project so that tasks' durations would not change if resources were added to them.

You showed during the session that you can set tasks to have 'fixed duration' or 'fixed units' or 'fixed work'. The former (fixed duration) I think we believed would be more useful to stop the aforementioned happening. However when we do this (select all tasks, shift F2 to go to task info, then set the task type), and having entered in an amount of 'work' for each task, when we change the resources on the task the work units change automatically. Also, it seems eventhough we have selected 'fixed duration', the duration changes when new work units are inputted.

I think what we would like is for both duration and work to be fixed when we enter in task data and then the have Project automatically adjust the resources . Is this possible?

Many thanks

Stuart

For upcoming training course dates see: Pricing & availability

replyReplyTue 9 Jun 2009, 10:11Trainer Andrew said...

RE: Resources, work and duration

Hi Stuart

Thank you for your question. At its core MS Project uses the formula:

Duration X Units of resource = Work

when working with resourced tasks.

The control we have over it is to fix one of the values prior to making an edit to one of the remaining two. Project is then left to recalculate the remaining value.

The formula kicks in when tasks that already have resources are edited. An alternative would be to remove your resources from the task in question, set the task values up as you wish then add your resources back onto the task at the unit levels you require. This circumvents MS Project tweaking your task but gives the Project Manager more work to do.

Microsoft have a small summary table that describes the impact of fixing / editing values in the formula.

http://office.microsoft.com/en-gb/project/HP100920391033.aspx?pid=CH100666551033

I hope this helps - do let us know if you have any further questions.


Kind regards,
Andrew

Mon 15 Jun 2009: Automatically marked as resolved.

 

 

Please browse our web site to find out more about
microsoft project training seminar and other Microsoft training courses.

Ms project tip:

Autofit column width – Project (all versions)

a. Highlight the column or columns you wish to alter the width of.
b. Double click the dividing line between the columns. This dividing line is the break between the columns on the column headers (grey buttons showing the column letter at the top of each column). When you hover your mouse over one of these dividing lines the point will change and show an arrow pulling a line in two directions. When you have this mouse pointer you should double click to get Project to automatically set the column width to fit the contents of the column (autofit)

View all MS Project hints and tips

forum postHI


I am working on a sheet with 2 columns and organizing these in a separate sheet.

firstly I am organizing in ASCENDING ORDER a long list with the following:

=LARGE(IF(('List clients'!$F$3:$F$482>" "),'List clients'!$K$3:$K$482),K..

» Forum post: INDEX, MATCH AND LARGE FORMULA


Rate this page:
2.2/5 (213 votes cast)
Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses
Microsoft Certified Partner
Security Seal verified by visa, mastercard securecard

Mini sitemap. These are the main areas of our web site. Full sitemap.

Management training

Professional Skills courses
Project Management Course London
Project Management Courses London
Project Management Training London
Project Management Training
Project Seminar
Project Seminars
Time Management Course London
Time Management London
Time Management Courses London
Time Management Training London
Introduction to Finance course
Assertiveness Skills course
Effective Communications Skills training
Presentation Skills London

Training Formats

Public scheduled courses
On-site training
Closed company courses

Consultancy
Application Development

Blogs

Excel Training
MS Project Training
Microsoft Training Blog

Version differences

Office 2010 vs 2007
MS Project version differences

Training Information

London Computer Training
Computer Training London
Docklands Training Courses
Docklands Training London

Training venues London
Client list
FAQ
Pricing and availability
Course details / Syllabus

Training Articles
Training Information

Microsoft training

Microsoft Office training
& IT Applications

Microsoft Project training
Microsoft Outlook training
Microsoft Powerpoint training
Microsoft Word training
MS Project courses
MS Project training
Outlook courses
PowerPoint courses
PowerPoint training
VBA courses
Word courses
Microsoft.training
(more...)

Excel Training

Excel courses
Excel Training Courses Medway
Autonumber in Excel
Microsoft Excel training
Basic Excel Courses
Basic Excel Course
Basic Excel Training

Interested in MS Access training?

Access courses
Microsoft Access training
Microsoft access courses
Microsoft training access course
Microsoft+access+training
Access courses in london

Training provider

Training providers
IT training companies
IT training providers
Management Training providers
Management Training provider

Event history, feedback results
Events in 2012 · 2011 · 2010 · More

See also

Crystal Reports training