Forum home » Delegate support and help forum » Microsoft Project Training and help » Start-to-finish relationship

Start-to-finish relationship

The UK's most regular instructor-led training courses.
Training information: project/server/2003/training · Project training · Microsoft Project Training London
See also · microsoft project training courses · microsoft.project.course · microsoft+project+courses

resolvedResolved · Low Priority · Version 2003

No ranking yet
1 post
replyReplyMon 8 Jun 2009, 16:23Delegate James said...

James has attended:
Project Introduction course

Start-to-finish relationship

Please can you explain and provide an example of when the start-to-finish is used?

Project Intro Intermediate 2 day course
Version Date Location Places
available
Book Next place rate (£)
Pay by
Card
Pay by
Invoice
2003 Thu 25 + Fri 26 Mar 2010 Bloomsbury 6 Book now £445 £450
2007 Wed 31 + Thu 1 Mar 2010 Bloomsbury 7 Book now £445 £450
2007 Mon 12 + Tue 13 Apr 2010 Limehouse 6 Book now £445 £450
2003 Wed 14 + Thu 15 Apr 2010 Bloomsbury 9 Book now £345 £350
2007 Mon 19 + Tue 20 Apr 2010 Bloomsbury 5 Book now £470 £475
2007 Tue 27 + Wed 28 Apr 2010 Limehouse 7 Book now £445 £450
Full Schedule: See all 32 Project Intro Intermediate course dates.
Bookings currently available until 20th December 2010.

Diamond
1,055 posts
replyReplyTue 9 Jun 2009, 09:46Trainer Andrew said...

RE: Start-to-finish relationship

Hi James

Thanks for your question. One example for this involves two tasks sitting an exam and revising for exam.

In this case the exam is in the future but is driving when the revision takes place, so the exam is the predecessor and the revision the successor.

It is the start of the exam that determines when the revision will finish. So the relationship between the tasks is Finish to Start.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Mon 15 Jun 2009: Automatically marked as resolved.


Related articles

· Managing multiple projects with MS project
· Plan your wedding with the help of Microsoft Project
· So What Printouts Can You Produce From Microsoft Project?
· Getting Your Project Started With Project
· The Critical Path in Microsoft Project

Please browse our web site to find out more about
project/server/2003/training and other Microsoft training courses.

Ms project tip:

Email a Task

When you need to communicate important information to your project staff use Microsoft Project 2003 to send them a note using outlook or an e-mail system.

1.In a task sheet, select the task or tasks which you want to send a project note.

2.On the File menu, point to Send To, and then select Mail Recipient (as Schedule Note).

3.Under Address message to, select the recipients of your note.

View all MS Project hints and tips


Rate this page:
2.1/5 (108 votes cast)
Institute of IT Training - Accredited Training Provider ILM
Microsoft Certified Partner
Microsoft Office Specialist Authorised Testing Centre (MOS and MCAS)

Prodigy Platinum Learning Partner

Institute of IT Training - Accredited Training Provider
McAfee Secure sites help keep you safe from identity theft, credit card fraud, spyware, spam, viruses and online scams
Association of Computer Trainers verified by visa, mastercard securecard