Resource
Resolved · Low Priority · Version 2003
Resource
How do you allocate tasks to different people/ job typesFor upcoming training course dates see: Pricing & availability
RE: Resource
Hi KarenIn MS Project the resource is assigned to the task, rather than the other way around.
One of the ways to do this is to split the screen (Window > Split) then click on a task. In the lower left pane of the split click below the column Resource Name then choose your resource from the list and click OK.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Mon 15 Jun 2009: Automatically marked as resolved.
|