Reminders
Is there a way for MSP to show pop ups to remind you that a task is overdue?For upcoming training course dates see: Pricing & availability
RE: reminders
Hi Sandra,Thank you for your question.
As far as I am concerned, you can't set up reminders in project to pop up when a task becomes overdue. Project does allow you to add a deadline date. When the finish date of the task is later than the deadline date, then a warning symbol appears in the Indicators column showing you the relevant information.
I hope this answers your question.
Regards
Simon
Thu 18 Jun 2009: Automatically marked as resolved.
|
|