Forum home » Delegate support and help forum » Microsoft Project Training and help » Reporting RAG against % task complete in Project
Reporting RAG against % task complete in Project
Resolved · Medium Priority · Version 2003
Reporting RAG against % task complete in Project
Hi thereI'm not sure whether this is possible... I think it might be but can you tell me if I can insert a column to show RAG status on how complete a task is?
Thanks
Sam
For upcoming training course dates see: Pricing & availability
RE: Reporting RAG against % task complete in Project
Hi Samantha, this is certainly possible but a little difficult to answer completely in a post here. However, have a look at the following thread on this forum:http://forums.techarena.in/microsoft-project/1001679.htm
...which should point you in the right direction!
Hope this helps,
Anthony
RE: Reporting RAG against % task complete in Project
Thanks Anthony. What I'm trying to achieve is much simpler than this I think...I am going to be manually changing the % complete column and I just want a formula to show the following:
C = 100%
G = 80-99%
A = 50-79%
R = 0-49%
I'm challenged when it comes to formulas so any further assistance would be fantastic.
Thanks
Sam
|
|