RE: Costs
Hi Patrick,Thank you for your question.
There are many answers to this question.
If you add the Project summary task to the Project and then change the table applied to the Gannt Chart to the Cost Table.
Now you will see the Total Cost field and the total cost for the Project Summary task.
Another way of achieving this is to go to the Project menu, Project Information and then Statistics.
I hope this answers your question.
Regards
Simon