Milestones
Resolved · Low Priority · Version 2007
Milestones
how do I move milestone dates on gantt chart?For upcoming training course dates see: Pricing & availability
RE: milestones
Hi Cath,Thank you for your question and welcome to the forum.
You can hover over the Milestone marker and drag it to a date in the future. Project will add a Start no earlier than constraint.
However, it is unlikely you would do this. Milestone tasks are usually linked to a predecessor task which means that if the predecessor task changes the milestone date would automtically update.
I hope this answers your question.
Regards
Simon