Forum home » Delegate support and help forum » Microsoft Project Training and help » Predecessors
Predecessors
Resolved · Low Priority · Version 2007
Predecessors
When would a start to finish dependancy occur?For upcoming training course dates see: Pricing & availability
RE: Predecessors
Hi Paul,Thank you for your question and welcome to the forum.
A start to finish relationship would be set if task(B) cannot be completed until the task it is dependent on(A) has begun.
Here is a link to an example:
http://office.microsoft.com/en-us/project/HA101130671033.aspx
I hope this helps and answers your question.
Regards
Simon
Thu 2 Jul 2009: Automatically marked as resolved.
|
|