Resourcing

The UK's most regular instructor-led training courses.
Training information: microsoft project training courses · Project training · Microsoft Project Training London
See also · microsoft project training courses · microsoft.project.course · microsoft+project+courses

resolvedResolved · Medium Priority · Version 2007

No ranking yet
1 post
replyReplyThu 25 Jun 2009, 16:11Delegate Chaitali said...

Chaitali has attended:
Project Intro Intermediate course

Resourcing

If you are unsure how much of a resources time will be available to you, I put in a percentage of the resource against each task, however this throuws questions at me and amends the units. is this the best way of assigning resources?

Project Advanced 1 day course
Version Date Location Places
available
Book Next place rate (£)
Pay by
Card
Pay by
Invoice
2003 Mon 19 Apr 2010 Southwark 9 Book now £295 £300
2003 Wed 4 Aug 2010 Southwark 10 Book now £295 £300
2003 Tue 30 Nov 2010 Southwark 10 Book now £295 £300

Platinum
642 posts
replyReplyThu 25 Jun 2009, 16:43Trainer Simon said...

RE: Resourcing

Hi Chaitali,

Thank you for your question and welcome to the forum.

I will have a look at your query tomorrow before we start training and then I will answer your question.

Regards

Simon

Platinum
642 posts
replyReplyMon 23 Nov 2009, 23:38Trainer Simon said...

RE: Resourcing

Hi Chaitali,

Thank you for your question and sorry for the delay in responding.

Have you found a way around your problem? Try the following:

If you go to Gantt chart view and use the window menu to split. In the bottom window choose the first resource from the left column and click OK.

Then edit either the unit or assign a particular amount of hours followed by OK again.

When you adjust the Unit the Hours will change and the same the other way round.

I hope this helps.

Regards

Simon

Mon 30 Nov 2009: Automatically marked as resolved.


Related articles

· Who is the Project Manager?
· Tracking Work Hours in Microsoft Project
· So What's New In Project 2007?
· MS Project, Helping Your Business Bloom
· Why Very Small Businesses Benefit from Microsoft Project Training Seminars

Please browse our web site to find out more about
microsoft project training courses and other Microsoft training courses.

Ms project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.

View all MS Project hints and tips


Rate this page:
2.1/5 (107 votes cast)
Institute of IT Training - Accredited Training Provider ILM
Microsoft Certified Partner
Microsoft Office Specialist Authorised Testing Centre (MOS and MCAS)

Prodigy Platinum Learning Partner

Institute of IT Training - Accredited Training Provider
McAfee Secure sites help keep you safe from identity theft, credit card fraud, spyware, spam, viruses and online scams
Association of Computer Trainers verified by visa, mastercard securecard