Project Overview - Project Summary Report
Resolved · Urgent Priority · Version 2003
Project Overview - Project Summary Report
Problem still unresolved. (see earlier posting today).I have amended the Resource Sheet to show the unit price per day and it STILL does not give logical answers.
eg ccy 200 per day should give me ccy 400 total for 2 man days. the result I get does not add up.
There must be another constraint that is defined elsewhere. I am using someone else's project plan btw.
PLEASE HELP!
For upcoming training course dates see: Pricing & availability
RE: Project Overview - Project Summary Report
Hi SarahThanks for the update - just out of training and got your message. Take a look at the Resource Usage view. Is your resource red (ie overallocated?) or are their hours on certain days edited so that there are more or less than the default 8 per day?
Have fixed costs been added to tasks? (insert the Fixed Cost column)
One way to trouble shoot the plan might be to change the day rate down to
|
|