I can't remember how to shunt the start date for the whole programme forward by 4 weeks.For upcoming training course dates see: Pricing & availability
RE: MS Project
Hi Neil,Thank you for your question and welcome to the forum.
If you want to change the Start Date of the project or programme, go to the Project menu and then Project Information.
Click on the Start Date calendar control and choose the new Start Date.
I hope this answers your question.
Regards
Simon