Resource allocation
Resolved · Low Priority · Version 2003
Resource allocation
can I track the use of a single resource over a number of projectsFor upcoming training course dates see: Pricing & availability
RE: resource allocation
Hi DeeThank you for your question. Yes you can. First create a project to store your resource information. Ideally it will have no tasks, just resources.
Then open your project that needs the resource and from the Tools > Resource Sharing > Share Resources
Set it to use resources from the resource pool file you created.
Your resource is then connected to the pool.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Mon 3 Aug 2009: Automatically marked as resolved.
|
|