Multiple tasks on same line
Resolved · Low Priority · Version 2003
Multiple tasks on same line
Further clarity on splitting single line tasks into multiple dates or groups for such things like quarterly cyclical maintenance visitsFor upcoming training course dates see: Pricing & availability
RE: Multiple tasks on same line
Hi BarryThank you for your question. MS Project has a recurring task feature that can help. Go to Insert > Recurring Task and use the selectors to decide the pattern for your recurring task. Project will then create constrained tasks that fall on the dates that meet the pattern you set.
Kind regards,
Andrew
Mon 3 Aug 2009: Automatically marked as resolved.
|
|