Can you breakdown the cost elements for Resourcing to showFor upcoming training course dates see: Pricing & availability
RE: Microsoft Project
Hi AnnThank you for your question. In practice the figure for standard rate would probably be set to include additional costs such as insurance so that it represents the cost to the project of having this resource.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Thu 6 Aug 2009: Automatically marked as resolved.
|
|