Work Breakdown Structure
Resolved · Low Priority · Version 2003
Work Breakdown Structure
How do you create task links?For upcoming training course dates see: Pricing & availability
RE: Work Breakdown Structure
Hi SolomonThank you for your question. There are several ways of creating links between your tasks. A robust approach is to double-click on the name of the successor task and from the predecessors tab select a suitable predecessor task. From the type box choose the relationship that suits your purpose and click OK.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Thu 6 Aug 2009: Automatically marked as resolved.
|
|