Baseline vs. Actuals
Resolved · High Priority · Version 2003
Baseline vs. Actuals
Progress lines to compare the progressFor upcoming training course dates see: Pricing & availability
RE: Baseline vs. Actuals
Hi James,Thank you for your question.
Are you using Progress lines to compare the progress?
You should be using the Tracking table in Gantt chart view to enter actual Start and Finish dates. Tyou can compare the actual plan to the baseline.
If so, go to Tools, Tracking and then Progress lines. In the bottom right of the dialogue box, make sure the 'Display progress lines in relation to baseline plan' checkbox is selected and not the actual plan.
I hope this answers your question.
Regards
Simon
Fri 7 Aug 2009: Automatically marked as resolved.
|
|