Critical tasks
Resolved · Low Priority · Version 2003
Meredy has attended:
Project Intro Intermediate course
Critical tasks
How do you show the critical tasks?
For upcoming training course dates see: Pricing & availability
RE: Critical tasks
Hi Meredy
Thank you for your question. A quick way to see the critical tasks in your plan is to swith to the Tracking Gantt view. You can do this from the View menu. Critical tasks will be coloured red.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew