Critical tasks

resolvedResolved · Low Priority · Version 2003

replyReply Thu 30 Jul 2009, 16:19Delegate Meredy said...

Meredy has attended:
Project Intro Intermediate course

Critical tasks

How do you show the critical tasks?

For upcoming training course dates see: Pricing & availability

replyReply Thu 30 Jul 2009, 17:00Trainer Andrew said...

RE: Critical tasks

Hi Meredy

Thank you for your question. A quick way to see the critical tasks in your plan is to swith to the Tracking Gantt view. You can do this from the View menu. Critical tasks will be coloured red.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Thu 6 Aug 2009: Automatically marked as resolved.

 

Please browse our web site to find out more about
project.training and other Microsoft training courses.

Ms project tip:

Project Community

in the help menu type "Tips" then select "Ask the Project community" this takes you into microsofts site where you can ask questions to lots of knowledgeable people.They make up an online group of experienced Project users who answer questions and provide solutions and tips.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard