Forum home » Delegate support and help forum » Microsoft Project Training and help » Task Information
Task Information
Resolved · Medium Priority · Version 2007
Richard has attended:
Project Intro Intermediate course
Task Information
What does the priority in the Task Info \ General mean?
For upcoming training course dates see: Pricing & availability
RE: Task Information
Hi Richard
Priority is used to give weighting to tasks as part of the leveling process (Tools > Level resources). Tasks with higher priorites (up to 1000) are not delayed whereas lower priority tasks are pushed back to deal with overallocation of resources.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Wed 26 Aug 2009: Automatically marked as resolved.
|