Forum home » Delegate support and help forum » Microsoft Project Training and help » Task Lists Reports

Task Lists Reports

resolvedResolved · Urgent Priority · Version 2003

replyReply Wed 9 Sep 2009, 10:31Delegate Jeff said...

Jeff has attended:
Powerpoint Intermediate Advanced course

Task Lists Reports

How do i produce a report that shows me the tasks lists / task to start on a week by week basis. i.e:

week 1 - tasks 1,2,3,4,5,6 etc
week 2 - tasks 7,8,9
week 3 - tasks 10,11 & 12

etc

For upcoming training course dates see: Pricing & availability

replyReply Wed 9 Sep 2009, 13:39Trainer Andrew said...

RE: Task Lists Reports

Hi Jeff

Thank you for your question. For individual resources you can do this by going to the View menu then choose Reports then select the Assignments group. In that list there will be a report called Todo which generates a list by resource

Alternatively you can export your task information to Excel (File > Save As then choose Excel workbook as your format). Follow the process to export Tasks and on the field mapping step click on Base on Table. From the list select the Entry table and finish the wizard. You can then open the exported Excel file and sort and group in Excel

Kind regards,
Andrew

Wed 16 Sep 2009: Automatically marked as resolved.

 

Please browse our web site to find out more about
ms project server consultancy and other Microsoft training courses.

Ms project tip:

Autofit column width – Project (all versions)

a. Highlight the column or columns you wish to alter the width of.
b. Double click the dividing line between the columns. This dividing line is the break between the columns on the column headers (grey buttons showing the column letter at the top of each column). When you hover your mouse over one of these dividing lines the point will change and show an arrow pulling a line in two directions. When you have this mouse pointer you should double click to get Project to automatically set the column width to fit the contents of the column (autofit)