Forum home » Delegate support and help forum » Microsoft Project Training and help » Project
Project
Resolved · Low Priority · Version 2003
Matthew has attended:
Project Intro Intermediate course
Project
If moving tasks between groups will dependencies be tailored accordingly
For upcoming training course dates see: Pricing & availability
RE: Project
Hi Matthew
Thank you for your question
If you move a task that has a predecessor or successor task to another line in the GANTT chart then all dependencies will be removed.
It is then however a simple matter to reinstate these links or change them as required.
Regards
Stephen
Fri 18 Sep 2009: Automatically marked as resolved.
|