Project

resolvedResolved · Low Priority · Version 2003

replyReply Thu 10 Sep 2009, 16:27Delegate Matthew said...

Matthew has attended:
Project Intro Intermediate course

Project

If moving tasks between groups will dependencies be tailored accordingly

For upcoming training course dates see: Pricing & availability

replyReply Fri 11 Sep 2009, 11:20Trainer Stephen said...

RE: Project

Hi Matthew

Thank you for your question

If you move a task that has a predecessor or successor task to another line in the GANTT chart then all dependencies will be removed.

It is then however a simple matter to reinstate these links or change them as required.

Regards

Stephen

Fri 18 Sep 2009: Automatically marked as resolved.

 

Please browse our web site to find out more about
project server consulting and other Microsoft training courses.

Ms project tip:

Format individual bars on your GANTT chart

To draw attention to a bar on your Gantt chart simply double click it. From the dialogue box that opens make your selection of text and bar modifications.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard