How do you decide on interdependencies between tasks
For upcoming training course dates see: Pricing & availability
RE: project
Hi Linda
Thank you for your question. One way is to double click on the successor task then go to the predecessor tab.
From here choose the predecessor task (that drives the successor) and decide if it is the start or finish of the predecessor that drives the start or finish of the successor. Choose the type of dependency that matches from the Type column.
I hope this helps - let us know if you have any further questions.
Kind regards,
Andrew