Forum home » Delegate support and help forum » Microsoft Project Training and help » Task that must remain at a fixed number of working hours

Task that must remain at a fixed number of working hours

resolvedResolved · Low Priority · Version 2007

replyReplyTue 6 Oct 2009, 16:18Delegate Dor said...

Task that must remain at a fixed number of working hours

I have two individuals working on Fixed Duration task that should take 70 hours over 10 days (7 hour working day). One individual is available to work 80% of the time on the task and the second individual is available 40% of the time. I have switched off effort driven scheduling and when I assign both individuals the total work hours adds up to 84 hours. How can alter the task to remain at 70 hours work using the 80% and 40% availability of my resources?

For upcoming training course dates see: Pricing & availability

replyReplyThu 8 Oct 2009, 14:02Trainer Andrew said...

RE: Task that must remain at a fixed number of working hours

Hi Dor

Thank you for your queston. I just want to check re the assignment. When you have the resources assigned and the work is distributed at 7 hours per day for ten days between your two resources what final percentage split are you looking for?
This will guide us with regard to the final assignment.

Kind regards,
Andrew

replyReplyThu 8 Oct 2009, 14:22Delegate Dor said...

RE: Task that must remain at a fixed number of working hours

Hi Andrew

Hadn’t thought about that originally, however, as long as Resource No. 1 is assigned at 80% or less and Resource No. 2 is assigned at 40% or less, I won't be concerned about the final outcome percentage split.

Many thanks
Dor




replyReplyThu 15 Oct 2009, 17:08Trainer Andrew said...

RE: Task that must remain at a fixed number of working hours

Hi Dor

Try this and see if it gives you the results you are looking for.

Set the task to fixed work. Split the screen (Window > Split) click on the task in questiion then set the task type to fixed work followed by OK.
Next assign you resources. You can assign them at the same time at their respective units of 80 and 40 followed by OK.

Project will then change the Duraton to allow for the two resources to complete 80 hours of work at their respective percentage units.

Let me know how you get on.

Kind regards,
Andrew

replyReplyThu 19 Nov 2009, 12:20Delegate Dor said...

RE: Task that must remain at a fixed number of working hours

Apologies for the tardy response. Yes it worked. Thank you very much.

Thu 22 Oct 2009: Automatically marked as resolved.

 

 

Please browse our web site to find out more about
consulting ms project and other Microsoft training courses.

Ms project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips

forum postHow do you pick out a text or characters within text or characters in a certain cell.

No set Left or Right indicators

» Forum post: Excel


Rate this page:
2.2/5 (213 votes cast)
Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses
Microsoft Certified Partner
Security Seal verified by visa, mastercard securecard

Mini sitemap. These are the main areas of our web site. Full sitemap.

Management training

Professional Skills courses
Project Management Course London
Project Management Courses London
Project Management Training London
Project Management Training
Project Seminar
Project Seminars
Time Management Course London
Time Management London
Time Management Courses London
Time Management Training London
Introduction to Finance course
Assertiveness Skills course
Effective Communications Skills training
Presentation Skills London

Training Formats

Public scheduled courses
On-site training
Closed company courses

Consultancy
Application Development

Blogs

Excel Training
MS Project Training
Microsoft Training Blog

Version differences

Office 2010 vs 2007
MS Project version differences

Training Information

London Computer Training
Computer Training London
Docklands Training Courses
Docklands Training London

Training venues London
Client list
FAQ
Pricing and availability
Course details / Syllabus

Training Articles
Training Information

Microsoft training

Microsoft Office training
& IT Applications

Microsoft Project training
Microsoft Outlook training
Microsoft Powerpoint training
Microsoft Word training
MS Project courses
MS Project training
Outlook courses
PowerPoint courses
PowerPoint training
VBA courses
Word courses
Microsoft.training
(more...)

Excel Training

Excel courses
Excel Training Courses Medway
Autonumber in Excel
Microsoft Excel training
Basic Excel Courses
Basic Excel Course
Basic Excel Training

Interested in MS Access training?

Access courses
Microsoft Access training
Microsoft access courses
Microsoft training access course
Microsoft+access+training
Access courses in london

Training provider

Training providers
IT training companies
IT training providers
Management Training providers
Management Training provider

Event history, feedback results
Events in 2012 · 2011 · 2010 · More

See also

Crystal Reports training