Forum home » Delegate support and help forum » Microsoft Project Training and help » Task that must remain at a fixed number of working hours

Task that must remain at a fixed number of working hours

The UK's most regular instructor-led training courses.
Training information: consulting ms project · Project training · Microsoft Project Training uk
See also · microsoft project training courses · microsoft.project.course · microsoft+project+courses

resolvedResolved · Low Priority · Version 2007

No ranking yet
3 posts
replyReplyTue 6 Oct 2009, 16:18Delegate Dor said...

Dor has attended:
Project Intro Intermediate course
Project Advanced course

Task that must remain at a fixed number of working hours

I have two individuals working on Fixed Duration task that should take 70 hours over 10 days (7 hour working day). One individual is available to work 80% of the time on the task and the second individual is available 40% of the time. I have switched off effort driven scheduling and when I assign both individuals the total work hours adds up to 84 hours. How can alter the task to remain at 70 hours work using the 80% and 40% availability of my resources?

Project Intro Intermediate 2 day course
Version Date Location Places
available
Book Next place rate (£)
Pay by
Card
Pay by
Invoice
2003 Thu 25 + Fri 26 Mar 2010 Bloomsbury 5 Book now £470 £475
2007 Wed 31 + Thu 1 Mar 2010 Bloomsbury 7 Book now £445 £450
2007 Mon 12 + Tue 13 Apr 2010 Limehouse 5 Book now £470 £475
2003 Wed 14 + Thu 15 Apr 2010 Bloomsbury 9 Book now £345 £350
2007 Mon 19 + Tue 20 Apr 2010 Bloomsbury 5 Book now £470 £475
2007 Tue 27 + Wed 28 Apr 2010 Limehouse 7 Book now £445 £450
Full Schedule: See all 32 Project Intro Intermediate course dates.
Bookings currently available until 20th December 2010.

Diamond
1,055 posts
replyReplyThu 8 Oct 2009, 14:02Trainer Andrew said...

RE: Task that must remain at a fixed number of working hours

Hi Dor

Thank you for your queston. I just want to check re the assignment. When you have the resources assigned and the work is distributed at 7 hours per day for ten days between your two resources what final percentage split are you looking for?
This will guide us with regard to the final assignment.

Kind regards,
Andrew

No ranking yet
3 posts
replyReplyThu 8 Oct 2009, 14:22Delegate Dor said...

RE: Task that must remain at a fixed number of working hours

Hi Andrew

Hadn’t thought about that originally, however, as long as Resource No. 1 is assigned at 80% or less and Resource No. 2 is assigned at 40% or less, I won't be concerned about the final outcome percentage split.

Many thanks
Dor




Diamond
1,055 posts
replyReplyThu 15 Oct 2009, 17:08Trainer Andrew said...

RE: Task that must remain at a fixed number of working hours

Hi Dor

Try this and see if it gives you the results you are looking for.

Set the task to fixed work. Split the screen (Window > Split) click on the task in questiion then set the task type to fixed work followed by OK.
Next assign you resources. You can assign them at the same time at their respective units of 80 and 40 followed by OK.

Project will then change the Duraton to allow for the two resources to complete 80 hours of work at their respective percentage units.

Let me know how you get on.

Kind regards,
Andrew

No ranking yet
3 posts
replyReplyThu 19 Nov 2009, 12:20Delegate Dor said...

RE: Task that must remain at a fixed number of working hours

Apologies for the tardy response. Yes it worked. Thank you very much.

Thu 22 Oct 2009: Automatically marked as resolved.


Related articles

· So What's New In Project 2007?
· Advanced Microsoft Project Training - manage your level of expertise
· Problem Solve On The Job With MS Project
· Dealing with Scope Creep in Microsoft Project
· Delegating Tasks Effectively In Microsoft Project

Please browse our web site to find out more about
consulting ms project and other Microsoft training courses.

Ms project tip:

Gantt Charts

Gantt Charts was first Invented by Henry Gantt (1861-1919) while planning the construction of U.S. Navy ships during WWI.hence the name Gantt Charts

View all MS Project hints and tips


Rate this page:
2.1/5 (108 votes cast)
Institute of IT Training - Accredited Training Provider ILM
Microsoft Certified Partner
Microsoft Office Specialist Authorised Testing Centre (MOS and MCAS)

Prodigy Platinum Learning Partner

Institute of IT Training - Accredited Training Provider
McAfee Secure sites help keep you safe from identity theft, credit card fraud, spyware, spam, viruses and online scams
Association of Computer Trainers verified by visa, mastercard securecard