resource shedule
Microsoft Office TrainingThe UK's Number 1 for Microsoft Office Training add this page to your favourites/bookmarksBookmark page

view a printable version of this pagePrintable version
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » Resource shedule

Resource shedule

The UK's most regular instructor-led training courses.
Training information: ms+project+server · Project training · Microsoft Project Training
See also · microsoft project training courses · microsoft.project.course · microsoft+project+courses

resolvedResolved · Low Priority · Version 2007

No ranking yet
1 post
replyReplyTue 27 Oct 2009, 16:42Delegate Ian said...

Resource shedule

Shared resource schedule and how to see if there is an excess of claim against those resources. Or even that sub projects can see how much labour has been claimed against that pool.

Project Advanced 1 day course
Version Date Location Places
available
Book Next place rate (£)
Pay by
Card
Pay by
Invoice
2003 Mon 19 Apr 2010 Southwark 9 Book now £295 £300
2003 Wed 4 Aug 2010 Southwark 10 Book now £295 £300
2003 Tue 30 Nov 2010 Southwark 10 Book now £295 £300

Platinum
633 posts
replyReplyWed 28 Oct 2009, 14:53Trainer Simon said...

RE: Resource shedule

Hi Ian,

Thank you for your question and welcome to the forum.

I am currently looking at your question and as soon as I have an answer I will email you.

Regards

Simon



Diamond
1,055 posts
replyReplyThu 3 Dec 2009, 11:47Trainer Andrew said...

RE: Resource shedule

Hi Ian

Thank you for your question - and apologies for the delay in coming back to you. One way to see both assignments across multiple projects and overallocation would be to open the resource pool and look at the resource usage view.

You can add in a column that shows the name of the sub project that contains each task (right click on the label for the task name and choose insert column. From the list select the field called Project).

Overallocation resources will be shown in red and the table will show when overallcation is taking place, across multiple projects.

I hope this helps - do let us know if you have any further questions.


Kind regards,
Andrew

Wed 9 Dec 2009: Automatically marked as resolved.


Related articles

· How To Start Working With Task Bars In Microsoft Project's Gantt Chart
· Three Ways to Make Microsoft Projects Courses More Effective
· Avoiding Project Failures
· Why Very Small Businesses Benefit from Microsoft Project Training Seminars
· The Jargon Of Project

Please browse our web site to find out more about
ms+project+server and other Microsoft training courses.

Ms project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.

View all MS Project hints and tips


Rate this page:
2.1/5 (107 votes cast)
Institute of IT Training - Accredited Training Provider ILM
Microsoft Certified Partner
Microsoft Office Specialist Authorised Testing Centre (MOS and MCAS)

Prodigy Platinum Learning Partner

Institute of IT Training - Accredited Training Provider
McAfee Secure sites help keep you safe from identity theft, credit card fraud, spyware, spam, viruses and online scams
Association of Computer Trainers verified by visa, mastercard securecard