Critical path
Can I view the critical path as original baseline and at current progress?For upcoming training course dates see: Pricing & availability
RE: Critical path
Hi JimThank you for your question. The built in views in Project include the Tracking Gantt view (View > Tracking Gantt) and this view shows current baseline with the live plan (which incorporates the critical path) overlayed above it.
MS Project calculates the critical path on the live project information rather than the baseline values. To keep a historical copy of the critical path along with the baseline you may want to save an archive copy of the plan that can be referred to once the main plan is updated.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Mon 9 Nov 2009: Automatically marked as resolved.
|
|
How To Use Functions In Excel 2010 As Excel has evolved, functions have remained a core feature, and using them is even easier than ever. This article summarises different ways a user can add a function, covering the traditional Insert Function panel, the new Formulas tab or by selecting one from the new pop down functions list. » Article: Excel training |