Forum home » Delegate support and help forum » Microsoft Project Training and help » Night Work
Night Work
Resolved · High Priority · Version 2003
Night Work
I have set up my project to use the night shift calendar but the gant chart does not show the work spreading across part of monday and into tuesday. how do I fix this?For upcoming training course dates see: Pricing & availability
RE: Night Work
Hi Stephen,Thank you for your question.
If you go to Format and then Timescale. If you need to, choose to display three tiers. Assign Days to the top tier, Hours to the Middle tier and the bottom tier to Minutes changing the count to 30.
This should then show you the start of the task beginning on the previous day running into the next morning.
I hope this answers your question.
Regards
Simon
Thu 26 Nov 2009: Automatically marked as resolved.
|
|
» Forum post: Excel |



Course updates

