Updating work done

resolvedResolved · Low Priority · Version 2007

replyReply Mon 14 Dec 2009, 16:09Delegate Piers said...

Piers has attended:
Project Intro Intermediate course

Updating work done

i have a nightmare trying to account for work done each day on a task. A task might be only a day long but could easily be done in hourly bits over a few days, but to account for this always seems to go wrong!

For upcoming training course dates see: Pricing & availability

replyReply Thu 17 Dec 2009, 07:51Trainer Andrew said...

RE: updating work done

Hi Piers

Thank you for your question. It sounds like you might have one day of Work to be carried out over several days of duration. You may find it easier to update your tasks by either Switching to the Resource Usage view then right clicking on the right hand table. From the menu that appears you will see an option to display Actual Work. Selecting this allows you to record what really took place, day by day. Project will adjust the Duration to reflect the changes you make.

Alternatively in the Gantt Chart view you may prefer to add the Actual and Remaining Work columns and progress your tasks that way.

Let me know how you get on and if you have any further questions.

Kind regards,
Andrew

replyReply Thu 17 Dec 2009, 08:53Delegate Piers said...

RE: updating work done

Thank you Andrew. The issue is usually with the way that updating actual work seems to keep throwing the duration and % complete values out completely, but I figured from the course that I just need to ignore this value ... would this be right?

replyReply Fri 18 Dec 2009, 16:57Trainer Andrew said...

RE: updating work done

Hi Piers

Thanks for coming back to me. Rather than ignore it I think maybe see it for what it is i.e. % duration complete. It's likely that you'll be more focussed on tracking actual work and remaining work.

Let me know how you get on.

Kind regards,
Andrew

 

Please browse our web site to find out more about
2003+microsoft+project+server and other Microsoft training courses.

Ms project tip:

Show or hide toolbar ScreenTips

On the Tools menu, go to Customize, and then select Toolbars.
Click the Options tab.
put a tick or remove the tick from the Show ScreenTips on toolbars check box.