critical paths
Microsoft Office TrainingThe UK's Number 1 for Microsoft Office Training add this page to your favourites/bookmarksBookmark page

view a printable version of this pagePrintable version
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » Critical paths

Critical paths

The UK's most regular instructor-led training courses.
Training information: microsoft project consulting · Project training · Microsoft Project Training
See also · microsoft project training courses · microsoft.project.course · microsoft+project+courses

resolvedResolved · Low Priority · Version 2007

No ranking yet
1 post
replyReplyMon 14 Dec 2009, 16:09Delegate Alexandra said...

Alexandra has attended:
Project Intro Intermediate course

Critical paths

How is the critical path calculated and how can I see it?

Project Advanced 1 day course
Version Date Location Places
available
Book Next place rate (£)
Pay by
Card
Pay by
Invoice
2003 Mon 19 Apr 2010 Southwark 9 Book now £295 £300
2003 Wed 4 Aug 2010 Southwark 10 Book now £295 £300
2003 Tue 30 Nov 2010 Southwark 10 Book now £295 £300

Diamond
1,055 posts
replyReplyThu 17 Dec 2009, 08:01Trainer Andrew said...

RE: Critical paths

Hi Alex

Thank you for your question.

The Critical Path in MS Project identifies those tasks that dictate when your plan will finish. They have no Slack which means if they change (duration, delay) your end date will also change.

You can quickly see the Critical Path by switching to the Tracking Gantt view (View > Tracking Gantt). Critical tasks are highlighted in red.

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

Tue 29 Dec 2009: Automatically marked as resolved.


Related articles

· Using Microsoft Project As Part Of Your Project Planning Strategy
· Microsoft Project Training: The Backbone of Effective Project Management
· What to Expect From Microsoft Project 2003 Training
· Microsoft Project Accessibility
· Basic Project Management Skills

Please browse our web site to find out more about
microsoft project consulting and other Microsoft training courses.

Ms project tip:

Entering Days

To type in a day of the week, or its three letter abbreviation, in a Date field type "Monday" or "Mon", and Project will show the date for the next Monday after the current date.

View all MS Project hints and tips


Rate this page:
2.1/5 (107 votes cast)
Institute of IT Training - Accredited Training Provider ILM
Microsoft Certified Partner
Microsoft Office Specialist Authorised Testing Centre (MOS and MCAS)

Prodigy Platinum Learning Partner

Institute of IT Training - Accredited Training Provider
McAfee Secure sites help keep you safe from identity theft, credit card fraud, spyware, spam, viruses and online scams
Association of Computer Trainers verified by visa, mastercard securecard