Critical paths
Resolved · Low Priority · Version 2007
Critical paths
How is the critical path calculated and how can I see it?For upcoming training course dates see: Pricing & availability
RE: Critical paths
Hi AlexThank you for your question.
The Critical Path in MS Project identifies those tasks that dictate when your plan will finish. They have no Slack which means if they change (duration, delay) your end date will also change.
You can quickly see the Critical Path by switching to the Tracking Gantt view (View > Tracking Gantt). Critical tasks are highlighted in red.
I hope this helps - do let us know if you have any further questions.
Kind regards,
Andrew
Tue 29 Dec 2009: Automatically marked as resolved.
|
|