microsoft+project+training - Milestone

resolvedResolved · Low Priority · Version Standard

replyReply Thu 22 Mar 2007, 13:33Delegate Luke said...

Luke has attended:
Project Introduction course
Project Introduction course

Milestone

How do I create the above?

For upcoming training course dates see: Pricing & availability

replyReply Thu 22 Mar 2007, 15:54Trainer Rich said...

RE: Milestone

Luke,

Thanks for the question.

To create a Milestone, enter a zero 0 day in the duration part of the task.

Good luck

Regards, Rich

 

Ms project tip:

Use Autofill in MS Project

a. Complete 1st entry
b. Select cell with entry to be copied
c. Click & drag autofill handle over the lines to also contain the same information. (the autofill handle is the little black square in the bottom right hand corner of the heavy lack outline on the selected cell)

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard