microsoft+project+courses+london - Milestone

resolvedResolved · Low Priority · Version Standard

replyReply Thu 22 Mar 2007, 13:34Delegate Gudrun said...

Gudrun has attended:
Project Introduction course
Project Introduction course

Milestone

How do I create the above?

For upcoming training course dates see: Pricing & availability

replyReply Thu 22 Mar 2007, 15:54Trainer Rich said...

RE: milestone

Gudrun,

Thanks for the question.

To create a Milestone, enter a zero 0 day in the duration part of the task.

Good luck

Regards, Rich

 

Ms project tip:

MS Project 2010 Scroll to Task

Ever feel lost on a large project file? In Gantt view, Task ribbon, Editing, click on the Scroll to Task tool to centre the task bar on your screen.

Shortcut Ctrl+Shift+F5

Same as Go to Selected Task in MS Project 2003.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard