Milestones

resolvedResolved · High Priority · Version 2007

replyReply Tue 6 Apr 2010, 12:28Delegate Damian said...

Damian has attended:
Project Intro Intermediate course

Milestones

I need to show a milestone at the start of a day rather than the end of the previous day while still using a soon as possible link.

An example is, there is a preconstruction phase to a building which finishes on a friday afternoon at 17:00. i need the start on site milestone to say start on site monday morning 8:00am. This is not a fixed date because if the preconstruction period can be shorted the start on site date can be brought forward. however I cannot show the start on site date being the friday afternoon at 17:00 as this is not when works will start on site.

i also cannot show the start on site date as a full day as this means all work starts on tuesday not monday.

It is a requirement of the client that I show a start on site milestone that accurately reflects the start on site date.

Any advice would be helpful

For upcoming training course dates see: Pricing & availability

replyReply Wed 7 Apr 2010, 14:25Trainer Andrew said...

RE: milestones

Hi Damian

Thank you for your question.

The milestone has no duration which is making it appear on Friday rather than on Monday. Try setting the duration of the milestone to 1 minute (1m) which turns it into a short blue bar. Then on the advanced tab for the milestone tick the Show as Milestone box. Now there is a duration so it will be forced to the next working day (Monday) but can move earlier in the schedule if the pre phase is shorter than planned.

Although this is a bit of a compromise does it help present things more clearly on the plan?

Kind regards,

Andrew

replyReply Wed 7 Apr 2010, 14:47Delegate Damian said...

RE: milestones

Does this mean i would have to reduce the next task by a minute to make sure it shows a completion of the right time or is a minute to small a time period for this to matter. Sounds like this may work though.

Regards

Damian

replyReply Fri 9 Apr 2010, 18:42Trainer Andrew said...

RE: milestones

Hi Damian

Thank you for coming back to me.

Unfortunately as this is a workaround there isn't an easy answer. In the end we are looking to find a way of making the chart look right. The milestone appearing at the end of Friday is just the way the software handles a zero duration task before non working time. Giving it a duration of 1 minute is enough to push it forwards but you will have a minute too much on Monday. Either way there is a compromise. In practice the milestone is often left with zero duration and although it appears to fall on Friday this is not a major problem as it will likely move again as the plan is updated.

I hope this helps,

Kind regards,
Andrew

Fri 16 Apr 2010: Automatically marked as resolved.

 

Please browse our web site to find out more about
project.training and other Microsoft training courses.

Ms project tip:

Using the Quick Access Toolbar in Project 2010

The Quick Access Toolbar is included in virtually every Office product, including Project 2010 as well as Outlook 2010, Word 2010, Excel 2010, and PowerPoint 2010.

You will find the Quick Access Toolbar in the top-left side of the window. To begin, click the Customize button (it's the little black arrow at the end of the toolbar).

Simply click the commands you want to include.

Virtually any command can be added to the Quick Access Toolbar. Click the More Commands option and a new window will open from where you can browse the commands including those not on the ribbon.

View all MS Project hints and tips