change standard calendar change
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » Change to standard calendar or change to resource working hours?

Change to standard calendar or change to resource working hours?

resolvedResolved · Medium Priority · Version 2007

replyReply Tue 6 Apr 2010, 15:07Delegate Caroline said...

Caroline has attended:
Project Intro Intermediate course

Change to standard calendar or change to resource working hours?

I oversee the timelines etc for 5 software developers who all work on several projects.

On the whole the decision has been taken to schedule them to work a 6 hour day (to take into account various factors that mean it is near on impossible to actually work a solid 8 hr day when developing). So for example if we quote a client '1 days work' I will be scheduling the developers for 8 hours - so this will span a day and a couple of hours. However, (typically this isn't always going to be the case) - as we do have the odd contract that has the developer on site for a specified number of days, so in this instance I would want the 'standard' calendar to apply.

My ideal is to have a resource sheet, then each project bought together on a master project - pulling the resource allocation through from the resource sheet.

My only confusion at the moment is whether I change the standard calendar on each project (or create a template to work from) showing this 6 hour working day, or if I should change each of my resources to show they only work a 6 hour day...?

Then what would I do in the instance where the six hour day doesn't apply?

hope that makes sense!

Caroline

For upcoming training course dates see: Pricing & availability

replyReply Wed 7 Apr 2010, 14:36Trainer Andrew said...

RE: Change to standard calendar or change to resource working ho

Hi Caroline

Because you mentioned you plan 1 day with clients as 8 hours but your developers allow 6 per day you might want to leave the standard calendar using 8 hours.

You could then create a special calendar called "6 hour day", that has hours reduced from the standard 8 hour day. Then set your resources on the Resource sheet to follow the 6 hour day calendar rather than standard.

Build your project and assign your resources. Once resources are assigned you will see how long the project will take. This also makes it easy to incorporate resources that do work 8 hours.

For those tasks that should run at 8 hours per day even though developers have been assigned - double click on the task name then in the advanced tab set the Calendar for that task to Standard and tick the box "Scheduling ignores resource calendar". Now everyone working on this task will work 8 hours per day regardless of their own base calendar.

There may be other ways to achieve this but does this get you closer to the result you are seeking?

Kind regards,
Andrew

 

Please browse our web site to find out more about
training.project.microsoft and other Microsoft training courses.

Ms project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard