Assigning Resources
When assigning resources to a task where I am putting more than one individual resource to each the task duration isnt calculating as expected. It works when I change units per resource but i wont be able to do that if i was using individual names.For upcoming training course dates see: Pricing & availability
RE: Assigning Resources
Try going to tools then Options and select the Schedule tabmake sure Effort driven is ticked in the middle of the Schedule tab and fixed units is selected try this first
|
|