microsft office project 2003 courses in london - lags
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » microsft office project 2003 courses in london - Lags

microsft office project 2003 courses in london - Lags

resolvedResolved · Low Priority · Version Standard

replyReply Tue 27 Mar 2007, 16:05Delegate Debra said...

Debra has attended:
Project Introduction course
Project Intermediate course

Lags

How do you create lags in Projects

For upcoming training course dates see: Pricing & availability

replyReply Thu 29 Mar 2007, 15:49Trainer Garry said...

RE: Lags

Double click on the arrow on the tasks and the TASK DEPENDENCY box appears select LAG

 

Ms project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.