resolvedResolved · Low Priority · Version Standard

replyReply Tue 27 Mar 2007, 16:06Delegate RONNIE said...

RONNIE has attended:
Project Introduction course
Project Intermediate course

Milestone

how do you link a milestone

For upcoming training course dates see: Pricing & availability

replyReply Thu 29 Mar 2007, 15:53Trainer Garry said...

RE: milestone

The same way as you link tasks
highlight the milestone and the task and select the link button on the tool bar

 

Ms project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.

View all MS Project hints and tips