course ms project - Lag

resolvedResolved · Low Priority · Version Standard

replyReply Tue 27 Mar 2007, 16:07Delegate Kate said...

Kate has attended:
Project Introduction course
Project Intermediate course

Lag

How do I add a lag to a task

For upcoming training course dates see: Pricing & availability

replyReply Thu 29 Mar 2007, 15:52Trainer Garry said...

RE: Lag

Double click on the arrow on the tasks and the TASK DEPENDENCY box appears select LAG

 

Ms project tip:

Autofit column width – Project (all versions)

a. Highlight the column or columns you wish to alter the width of.
b. Double click the dividing line between the columns. This dividing line is the break between the columns on the column headers (grey buttons showing the column letter at the top of each column). When you hover your mouse over one of these dividing lines the point will change and show an arrow pulling a line in two directions. When you have this mouse pointer you should double click to get Project to automatically set the column width to fit the contents of the column (autofit)

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard