Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project training london - Outdenting on MS Project Standard

ms project training london - Outdenting on MS Project Standard

resolvedResolved · Low Priority · Version Standard

replyReply Wed 28 Mar 2007, 16:06Delegate Paul said...

Paul has attended:
Project Introduction course
Project Intermediate course

Outdenting on MS Project Standard

I am struggling to outdent on MS Project Standard 2003? In particular the task directly below a summary level.

For upcoming training course dates see: Pricing & availability

replyReply Wed 28 Mar 2007, 16:08Delegate Simon said...

RE: Outdenting on MS Project Standard

I think this could be related to the service pack. Update to SP1 or SP2. It is a known Microsoft bug.

Simon

 

Ms project tip:

Link tasks using predecessor column - project

a. First, note ID number of the task you want to link to (predecessor). Then, in the predecessor column of the task you want to link to (successor), type the predecessor task's ID number.
b. The link will be a Finish to Start (the default type).
c. Or you can add in a code for a different relationship type
i. SS = Start to Start
ii. FF = Finish to Finish
iii. SF = Start to Finish
d. You don't have to type the task ID numbers in any specific order, but you must separate multiple tasks with commas.

View all MS Project hints and tips