assigning resource activity
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » Assigning a % of a resource to an activity

Assigning a % of a resource to an activity

resolvedResolved · Medium Priority · Version 2003

replyReply Tue 17 Aug 2010, 16:47Delegate Gar-yun said...

Gar-yun has attended:
Project Intro Intermediate course

Assigning a % of a resource to an activity

Hi
I have created an activity and have assigned a resource and when I enter a percentage in the units column in % to 2 decimal points it rounds up to the nearest whole number. Is there any way that I can change this to show 2 decimal points.
Thanks,
G

For upcoming training course dates see: Pricing & availability

replyReply Mon 23 Aug 2010, 17:01Trainer Andrew said...

RE: Assigning a % of a resource to an activity

Hi Gar-yun

Thank you for your question. The rounding occurs because MS Project is converting values to and from minutes (the unit it works with in the background). You may find you get more precision by using minutes as your own default unit - you can set this in Tools > optons > schedule but it will make the plan tricky to read/maintain.

Kind regards,
Andrew

replyReply Mon 23 Aug 2010, 17:01Trainer Andrew said...

RE: Assigning a % of a resource to an activity

Hi Gar-yun

Thank you for your question. The rounding occurs because MS Project is converting values to and from minutes (the unit it works with in the background). You may find you get more precision by using minutes as your own default unit - you can set this in Tools > opitons > schedule but it will make the plan tricky to read/maintain.

Kind regards,
Andrew

replyReply Mon 23 Aug 2010, 17:01Trainer Andrew said...

RE: Assigning a % of a resource to an activity

Hi Gar-yun

Thank you for your question. The rounding occurs because MS Project is converting values to and from minutes (the unit it works with in the background). You may find you get more precision by using minutes as your own default unit - you can set this in Tools > options > schedule but it will make the plan tricky to read/maintain.

Kind regards,
Andrew

Mon 30 Aug 2010: Automatically marked as resolved.

 

Please browse our web site to find out more about
installing ms project server and other Microsoft training courses.

Ms project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard