Recurring Task

resolvedResolved · Urgent Priority · Version 2003

replyReply Wed 1 Sep 2010, 17:19Delegate Gar-yun said...

Gar-yun has attended:
Project Intro Intermediate course

Recurring Task

I have a master project consisting of linked projects to the resource pool. I have a recurring task and it

1. ocurrs every monday till end of the year
2. lasts 1/2 day so have set the duration as 0.5day in the recurring task information box.

when i assign resources say Bob and Jim do i:

1. Change the duration to 1 day in the task information box
2. set the activity as fixed work
3. Put the "unit" as 50%.

The reason why i ask is because when i set the activity up to have a 0.5 day duration, change the tasks to fixed work and add a resource and allocate 100% in the unit column, it makes that person 100% for that day rather than making them 50% allocated

Thanks,
G

For upcoming training course dates see: Pricing & availability

replyReply Fri 3 Sep 2010, 09:27Trainer Jacob said...

RE: Recurring Task

Hi Gar-yun

Thank you for your post. I will need to run this by one of our lead Project trainers.

Can I just check that you have updated the resource calendar with regards the working time of this resource?

Kind regards

Jacob

replyReply Fri 3 Sep 2010, 09:33Delegate Gar-yun said...

RE: Recurring Task

Hi Jacob,
Yes calenders are up-to-date.
Thanks,
G

replyReply Thu 16 Sep 2010, 09:08Trainer Andrew said...

RE: Recurring Task

Hi Gar-Yun

Thank you for your question - as an alternative to fixed work how about trying fixed duration (as the meeting will be half a day ) then assigning your resources. I think you will find they are assigned at 50% of their max capacity.

Let me know how you get on.

Kind regards,
Andrew

Wed 22 Sep 2010: Automatically marked as resolved.

 

Please browse our web site to find out more about
microsoft project training seminar and other Microsoft training courses.

Ms project tip:

Formatting Bar Text

To display notes or resource initials on the Gantt chart bars, choose Format, Bar Styles and the Text tab. Select the position you want to show the text i.e. Top or Inside etc, then choose the field name you are looking for from the drop down arrow. Type the first letter of the name to get quickly to the top of the letter range. Click OK.