MS Project 2010 - Insert a New Task

resolvedResolved · Low Priority · Version 2010

replyReply Thu 9 Sep 2010, 16:23Delegate Jon said...

Jon has attended:
Project Intro Intermediate course

MS Project 2010 - Insert a New Task

I sometimes need to insert a task at late notice, this new task is fixed re: start date and end date. I'd like this to autosplit the task/s it interrupts. If there's a macro I could use to do this or some internal functionality I could use - this would be excellent.

For upcoming training course dates see: Pricing & availability

replyReply Wed 15 Sep 2010, 15:13Trainer Andrew said...

RE: MS Project 2010 - Insert a New Task

Hi Jon

Thank you for your question - there isn't an autosplit function that I'm aware of. The MSDN website has a programming reference guide that explores the changes in Project 2010 and might be a good place to start.

http://msdn.microsoft.com/en-us/library/ee758031.aspx

I hope this helps - do let us know if you have any further questions.

Kind regards,
Andrew

replyReply Fri 17 Sep 2010, 12:37Trainer Nafeesa said...

Will be marked as resolved in 5 days

Notice: This is an automated message. Due to inactivity, this forum post will be marked as 'resolved' if there are no further responses in the next 5 days.

replyReply Fri 17 Sep 2010, 13:28Delegate Jon said...

RE: MS Project 2010 - Insert a New Task

Thanks Andrew, as we discussed (in person) as a development team specialist I'm sure we could work this out for ourselves, I was just optimistic that I wasn't alone in this requirement and therefore someone else may have found a solution that works already. (This could potentially save us a lot of development time).

But heres my current thinking:

If I was to insert it as non-working time - this would lengthen the duration of a task which is more or less the same result - I can categorise my non-working time and presumably report on it by it's category.

Here's the bit of info I probably should have mentioned; this "interrupting task" is typically non-development so it doesn't have to be recorded/tracked or planned in the same way as the original plan - so doing it as non-working time would work for me. Having said that I could still plan for it - my issue then becomes - how can I see different types of non-working time highlighted differently on the plan - currently it's all one format on screen isn't it?

So my conclusion is: I would *LOVE* to see different non-working time formatted differently - such that weekends can keep the default of grey (if I wanted) and holidays are a different colour, sickness a third colour, and these interrupting tasks a fourth colour (obviously there could be more potentially). This would be perfectissimo!



replyReply Mon 27 Sep 2010, 10:59Trainer Andrew said...

RE: MS Project 2010 - Insert a New Task

Hi Jon

Thanks for your reply and further info. Here is an article from the Microsoft Project Server blog. Project server 2010 has a "non-project working time" feature called administrative time that can be categorised. Is this closer to the features you are looking for (bearing in mind it does depend on Project Server 2010)?

http://blogs.msdn.com/b/project/archive/2009/02/13/administrative-time-explained.aspx

Kind regards,
Andrew

Sun 3 Oct 2010: Automatically marked as resolved.

 

Please browse our web site to find out more about
project 2007 server training and other Microsoft training courses.

Ms project tip:

Autofit column width – Project (all versions)

a. Highlight the column or columns you wish to alter the width of.
b. Double click the dividing line between the columns. This dividing line is the break between the columns on the column headers (grey buttons showing the column letter at the top of each column). When you hover your mouse over one of these dividing lines the point will change and show an arrow pulling a line in two directions. When you have this mouse pointer you should double click to get Project to automatically set the column width to fit the contents of the column (autofit)