Forum home » Delegate support and help forum » Microsoft Project Training and help » Select a Baseline to track against
Select a Baseline to track against
Resolved · High Priority · Version 2003
Gar-yun has attended:
Project Intro Intermediate course
Select a Baseline to track against
I have saved a baseline to "Baseline" and another to "Baseline 1". I want to view my current progress against "Baseline 1" how can I do this?
Thanks,
G
For upcoming training course dates see: Pricing & availability
RE: Select a Baseline to track against
Hi Gar-Yun,
Thank you for your question.
If you go to Gantt Chart View and apply the Cost table, you can add the Baseline 1 Cost field to comapre against Total Cost.
Alternatively go to the Variance table in Gantt Chart view and add the Baseline 1 Start and Baseline 1 Finish columns and compare them against Start and Finish.
If you go to Tracking Gantt view and double click into the white space you should be able to change the baseline from the Baseline to Baseline 1.
I hope this answers your question.
Regards
Simon
Tue 21 Sep 2010: Automatically marked as resolved.
|