ms project courses - milestones
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project courses - Milestones

ms project courses - Milestones

resolvedResolved · Low Priority · Version Standard

replyReply Tue 3 Apr 2007, 13:40Delegate Rachel said...

Rachel has attended:
Project Intro Intermediate course
Project Intro Intermediate course

Milestones

What classifies as a milestone?

For upcoming training course dates see: Pricing & availability

replyReply Wed 4 Apr 2007, 10:31Trainer Tracy said...

RE: Milestones

Hi Rachel,

Thanks for the question

Sometimes there are events external in your project that you may want to track. If you cannot link (establishing a connection between tasks. Linking tasks means a dependency between their start and finish dates) to them because they are not in a Project plan, you can create a milestone to represent them in your own project.

Hope that helps

Tracy

 

Ms project tip:

Inserting Task Durations Quickly

When entering durations for your tasks simply use the single letters - m for min, h for hr, d for day, w for week, but mon for month. If default is set for days, you need only type the number, for example 3 for 3days, or 0.5 for half a day.