ms project and ms visio training in london - predesessor
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » ms project and ms visio training in london - Predesessor

ms project and ms visio training in london - Predesessor

resolvedResolved · Low Priority · Version Standard

replyReply Tue 3 Apr 2007, 13:41Delegate Angela2 said...

Angela2 has attended:
Project Intro Intermediate course

Predesessor

What is a predecessor?

For upcoming training course dates see: Pricing & availability

replyReply Thu 5 Apr 2007, 16:11Trainer Tracy said...

RE: Predesessor

Hi Angela,

Occasionally you may choose Project to calculate a schedule a slightly differently than it would do naturally based on what has happened before.

This code takes the predecessors of a selected tasks and figures out which is the one which will finish first. Then it applies negative lag to the dependencies between itself and the other predecessors.

Hope that makes sense

Tracy

 

Ms project tip:

Typing Links Between Tasks

In the Entry table, use the Precessors column to type in links. Type the previous task's ID to link. To change the link, add FS (Finish-Start), FF (Finish-Finish), and so on, and + duration to add a Lag, or - duration for a Lead time. Example: for task 5, 4FS+1w ... task 4 preceeds task 5, finish to start, with a week lag between.