Holiday Exceptions

resolvedResolved · Low Priority · Version 2003

replyReply Mon 8 Nov 2010, 16:37Delegate Jen said...

Jen has attended:
Project Intro Intermediate course

Holiday Exceptions

How can I effectively insert staff holidays into my GANTT chart so that it is not possible to allocate them when they have holiday booked?

For upcoming training course dates see: Pricing & availability

replyReply Tue 9 Nov 2010, 10:33Trainer Rodney said...

RE: Holiday Exceptions

Hello Jen,

Thank you for your question regarding assigning staff holidays to your Gantt chart.

Presumably you have already set up your resources in the Resource Sheet view. Go to this view and double click on the resource you wish to edit and click the 'Working Time' tab. Select the working days for the resource which need to be changed and click the radio button 'Nonworking Time'.

When you assign this resource to a task which falls over the nonworking time period MS Project will pass over the holiday period which you have marked in the resource calendar.

Please remember though, that if the task begins before the resource starts their holiday period MS Project will assign the resource to the first few days of the task and then the resource will be assigned to the balance of the task after the holiday period ends. This in effect could extend the entire project so you have to decide whether it would be better to assign a different resource to this task or use more than one resource.

I hope this resolves your question. If it has, please mark this question as resolved.

If you require further assistance, please reply to this post. Or perhaps you have another Microsoft Office question?

Have a great day.
Regards,

Rodney
Microsoft Office Specialist Trainer

 

Please browse our web site to find out more about
project-server-training and other Microsoft training courses.

Ms project tip:

Autofit column width – Project (all versions)

a. Highlight the column or columns you wish to alter the width of.
b. Double click the dividing line between the columns. This dividing line is the break between the columns on the column headers (grey buttons showing the column letter at the top of each column). When you hover your mouse over one of these dividing lines the point will change and show an arrow pulling a line in two directions. When you have this mouse pointer you should double click to get Project to automatically set the column width to fit the contents of the column (autofit)