MS PROJECT 2010 IMPORT TO EXCEL

resolvedResolved · Low Priority · Version 2010

replyReply Wed 24 Nov 2010, 15:48Delegate Vanita said...

Vanita has attended:
Project Intro Intermediate course

MS PROJECT 2010 IMPORT TO EXCEL

Please can you let me know how to import the excel sheets into MS proj 2010

Thanks
Vanita

For upcoming training course dates see: Pricing & availability

replyReply Mon 29 Nov 2010, 09:35Trainer Simon said...

RE: MS PROJECT 2010 IMPORT TO EXCEL

Hi Vanita,

Thank you for your question.

To start the Import Wizard you need to follow these steps:

1. Go to File and Open.
2. Select Excel Workbook from File Types and select the Excel workbook and click Open.
3. This will start the Import Wizard and follow the steps through.
4. When you get to the Task mapping screen you need to choose which worksheet contains the data you want in project.
5. You then need to choose and map the fields from Excel into Project fields.

I hope this answers your question.

Regards

Simon

Sun 5 Dec 2010: Automatically marked as resolved.

 

Please browse our web site to find out more about
exchange server 2003 distant learning and other Microsoft training courses.

Ms project tip:

Gantt Charts

Gantt Charts was first Invented by Henry Gantt (1861-1919) while planning the construction of U.S. Navy ships during WWI.hence the name Gantt Charts