MSP

resolvedResolved · Low Priority · Version 2007

replyReply Fri 26 Nov 2010, 10:04Delegate Nick said...

Nick has attended:
Project Intro Intermediate course

MSP

I have downloaded a 30 DAY demo version of MSP 2007 to use whilst in between jobs.

I am unable to open the IMG file. Any ideas on what to do?

For upcoming training course dates see: Pricing & availability

replyReply Mon 29 Nov 2010, 09:09Trainer Simon said...

RE: MSP

Hi Nick,

Thank you for your question.

Try Virtual Clone Drive or Magic ISO to try and open the IMG file.

I hope this helps.

Regards

Simon

replyReply Thu 2 Dec 2010, 13:04Delegate Nick said...

RE: MSP

I tried this but it didnt work.

I have managed to download a demo of 2010 as an exe file and got that working. It s a bit different but I am finding my way around. One thing I cant find the answer to is how do you create a calender in MSP 2010?

Regards, Nick

replyReply Thu 2 Dec 2010, 16:50Trainer Simon said...

RE: MSP

Hi Nick,

Thanks for the update.

If you go to the Project tab and then choose Change Working Time. In the top right corner there is an option to create a new calendar.

I hope this answers your question.

Regards

Simon

replyReply Fri 10 Dec 2010, 09:12Delegate Nick said...

RE: MSP

Thanks I have created the calender and added non working days etc but how do you apply that calender for all tasks and resources in the project?

Cheers Nick

replyReply Sun 12 Dec 2010, 22:18Trainer Simon said...

RE: MSP

Hi Nick,

Thank you for your response.

If you go to Project and Project Information and choose your new calendar from the list.

Change the calendar for the first resource in the resource sheet and use the autofill handle to fill the rest.

Then any tasks that have resources assigned to them will be using your new calendar.

Regards

Simon

Thu 9 Dec 2010: Automatically marked as resolved.

 

Please browse our web site to find out more about
microsoft professional project server training and other Microsoft training courses.

Ms project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.