ms project resources leveling
The UK's Number 1 for Microsoft Office Training Add this page to your favourites/bookmarksBookmark page
 
View printable version of pagePrintable version
Plus One Google
Customer: Sign in
Delegate: Sign in
Trainer: Log in

Forum home » Delegate support and help forum » Microsoft Project Training and help » MS Project resources, leveling

MS Project resources, leveling

resolvedResolved · Urgent Priority · Version 2007

replyReply Mon 29 Nov 2010, 21:11 Edited on Thu 2 Dec 2010, 17:27Delegate Igors said...

Igors has attended:
Project Intro Intermediate course

MS Project resources, leveling

Hello!

There is one Task (fixed work) with an assigned working resource (person/persons) and some duration.
I would like to decrease duration of the Task by adding more resources, so I use additional person/persons which are finishing other tasks and becoming available (later! than start date of the Task but till the end of the Task will be available).
After that there is overallocation (new resource was busy few days from start of the Task) which was resolved by leveling.
As result we have resources with equaling hours and different start and finish dates.
But I need to have one finish date for all resources (Task must be finished by all persons).
Is there a correct way to do this? Is it possible to do this automaticaly?

Thank you!
Igor

For upcoming training course dates see: Pricing & availability

replyReply Mon 13 Dec 2010, 13:38Trainer Andrew said...

RE: MS Project resources, leveling

Hi Igor

It sounds like leveling is doing its best to keep the resouce allocation within the max units for each resource, however to achieve this work is being carried out over a longer time frame than you'd like. Resources are alos finishing on different days.

Part of the problem may be the default behaviour of Project to start and finish tasks as early as possible.

One approach could be to try a different constraint e.g. As Late As Possible, immediately followed by a milestone with Start No Earier Than set to a date that makes sense to your project. Better yet if you create an example file showing the problem you are encountering and send it to info for the attention of Andrew and I will have a look at it.

Kind regards,
Andrew

replyReply Wed 15 Dec 2010, 12:46Delegate Igors said...

RE: MS Project resources, leveling

Hi, Andrew!

Thanks,
I have e-mail files for You.

Kind regards,
Igor

 

Please browse our web site to find out more about
project.training and other Microsoft training courses.

Ms project tip:

Keep constraining dates to a minimum

As far as possible avoid fixing the dates of your tasks. For example try to steer of clear dragging task bars in the Gantt chart to move them on the timeline or entering dates directly into the Start / Finish fields.

Date constraints such as these limit Microsoft Project's ability to automatically adjust your project whenever you add, remove or modify the duration of your tasks. Instead use the logic in your task dependencies that link your tasks to enable Project to calculate the start and finish dates for you.

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard