Working time.

resolvedResolved · High Priority · Version 2007

replyReply Tue 30 Nov 2010, 11:49Delegate Shonna said...

Shonna has attended:
Project Intro Intermediate course

Working time.

For some reason my plan thinks Sunday is a working day and I don't know how to swich it off. I have checked the calendar and it says it is a non working day. But when I place a task on the plan the resource is working through Sunday!

For upcoming training course dates see: Pricing & availability

replyReply Thu 2 Dec 2010, 10:45Trainer Simon said...

RE: Working time.

Hi Shonna,

Thank you for your question and welcome to the forum.

There may be three reasons to why this is happening:

1. When a task is 6 days and starts on Thursday, the task would finish on the Thursday of the next week. The Gantt bar will stretch across the non working time (Sat and Sun).

2. Check Tools and Change Working Time. See if there are any exceptions that make the Sunday a working day.

3. Go to the Resource sheet and double click on the resource you assigned the task to. Click on the Change Working Time button and check whether there are any exceptions to the rule.

I hope this helps.

Regards

Simon

 

Please browse our web site to find out more about
training.project.microsoft and other Microsoft training courses.

Ms project tip:

Change default view – Project 2010

a. In Project, click on the File tab
b. Select General from left hand side (this should be the screen displayed by default)
c. Set the Default view dropdown box to your chosen option
d. Click OK to apply your changes

View all MS Project hints and tips


Microsoft Certified Partner Accredited Training Provider: Institute of IT Training Institute of Leadership and Management - Certified Courses Security Seal verified by visa, mastercard securecard